Set Up the Indoor Unit Condensate Piping Connections for Quantum Ultra Ceiling Cassette (CYT-24) systemsUpdated 2 hours ago
Introduction
This article explains how to set up the indoor unit condensate piping connections for Quantum Ultra Ceiling Cassette (CYT-24) systems.
Drain Pipe and Insulation Material Requirements
- Drain Pipe: Polyvinyl chloride (PVC) pipe with an 1-¼ inch outer diameter (32 mm).
- Heat Insulation: Foamed polyethylene insulation with a minimum thickness of ⅜ inch (10 mm).
Notes
- Insulate all drain piping and connections to the indoor unit to prevent dew formation and dripping.
- Maintain a continuous downward slope of more than ¼ inch per feet (minimum slope ratio of 1/50) with no dips, sags, or reverse slopes.

- Install support straps or brackets every 5-6.5 feet (1.5-2 m) along horizontal runs to main proper slope and prevent sagging.

- Keep the horizontal pipe length under 65 feet (20 m).
- Maintain a gap of approximately ⅜ inch (10 mm) between parallel pipes if installed side-by-side.

Install the Flexible Hose
- Measure the diameter of the hard pipe using a pipe cutter, then adjust the joining angle as needed.
- Extend the flexible hose to the required length without excessive deformation as shown below:

- Secure the flexible hose firmly using the provided hose band.

- Install the flexible hose in an horizontal orientation to ensure proper drainage. The maximum bending angle is 45°.
Connection Procedure
- Connect the transparent flexible hose to the PVC drain pipe.
- Apply PVC adhesive to the connection point between the drain pipe and flexible hose to ensure a watertight seal.
- Apply the adhesive approximately 1-½ inches (38 mm) from the end of the PVC pipe, then insert it into the flexible hose.
- Allow at least 10 minutes for the adhesive to cure. Do not apply pressure to the joint during the drying period.
Heat Insulation
- Wrap the entire length of the flexible hose carefully with the provided heat insulation material. Start from the flexible hose and continue to the indoor unit connection.
- Ensure that there are no gaps or exposed sections that could cause condensation.
- Use additional insulation material if necessary to fully cover all piping and connections.
Upward Drainage Installation
- The maximum vertical rose of the drainage pipe should not exceed 30 inches (762 mm).
- Maintain a horizontal extension from the indoor unit drain outlet of less than 4 inches (102 mm) before rise.

After the Installation is Completed
After the installation is finished, check the condensate drain line for leaks and proper drainage. If a condensate pump has been installed, check it to ensure proper operation. Pour water into the drain pan through the inspection port to confirm flow.
Note: A condensate pump is not provided with the system.