Install the Hanging Bolt for Quantum Ultra Ducted Ceiling Concealed SystemsUpdated 3 hours ago
Introduction
This article explains how to install the hanging bolts for Quantum Ultra Ducted Ceiling Concealed (RYT-24) systems.
Steps
Use four ⅜ inch threaded hanging bolts and eight washers and nuts to suspend the indoor unit. The hanging bolts are not included with the system.
The center-to-center distance between bolts must match the specifications provided for the unit size.
Ceiling Structure Mounting Methods
Finished Concrete (Brick or Slab)
- Use expansion bolts to fix the hanging hooks directly into the concrete.
- Drill a hole to a depth of 45-50 mm to ensure anchoring.

New Concrete Bricks
- Use one of the following methods to embed the screw bolts:
- Blade-type insertion
- Slide-in channel insertion
- Ensure the screw bolts are anchored firmly into embedded steel reinforcements bars.

Steel Roof Beam Structure
- Install supporting angle steel brackets.
- Mount the hanging bolts through the brackets and secure as shown below:

Wooden Construction
- Secure angle iron across the wooden joints.
- Secure the hanging screw bolts through the channel and into the ceiling structure below.